Search found 14 matches
- March 10th, 2017, 4:53 pm
- Forum: Civil Construction
- Topic: Electric pole issue near the site
- Replies: 20
- Views: 32610
Re: Electric pole issue near the site
I did undergo the same pain and paid 9k for shifting the electric pole which was in wrong position. BESCOM doesn't do the job , instead a work order gets created for this job and is outsourced to contractors. Again contractors and AE go hand-in-hand. Better to negotiate and bring down the price ...
- February 13th, 2017, 8:44 pm
- Forum: Civil Construction
- Topic: House Construction - Pre Approval Work Process
- Replies: 15
- Views: 19324
Re: House Construction - Pre Approval Work Process
You will be getting a NOC copy indicating an approval from BBMP, 6-7 copies of Blue Print of your Plan
- February 13th, 2017, 8:42 pm
- Forum: Civil Construction
- Topic: Need opinion on current tiles and granite laying charges
- Replies: 15
- Views: 22560
Re: Need opinion on current tiles and granite laying charges
I just agreed on the deal with only labor payment, materials will be supplied by me
Granite - INR 16/sft
Elevation Tiles/Bathroom/Kitchen/Parking - INR 12/sft
The current market rate from what i have come across is, Granite - 20 rupees and Tiles - 15 rupees. May be rate depends from place to place ...
Granite - INR 16/sft
Elevation Tiles/Bathroom/Kitchen/Parking - INR 12/sft
The current market rate from what i have come across is, Granite - 20 rupees and Tiles - 15 rupees. May be rate depends from place to place ...
- December 8th, 2016, 8:40 pm
- Forum: Civil Construction
- Topic: Must have electrical points for new house
- Replies: 3
- Views: 4864
Re: Must have electrical points for new house
You can go for spot light boxes. Single spot light box will cost you ~140 INR which adds decent looks in hall
- December 8th, 2016, 8:38 pm
- Forum: Civil Construction
- Topic: Must have electrical points for new house
- Replies: 3
- Views: 4864
Re: Must have electrical points for new house
1. Rooms to 2 way switches
2. Modular good night lamp points in rooms
3. AC points in rooms and halls
4. UPS provision
5. power points in parking garage for vaccum cleaners
6. general lighting areas
7. Kitchens to have atleast two power points (plan for fridge, oven, mixer, grinder, chimney and ...
2. Modular good night lamp points in rooms
3. AC points in rooms and halls
4. UPS provision
5. power points in parking garage for vaccum cleaners
6. general lighting areas
7. Kitchens to have atleast two power points (plan for fridge, oven, mixer, grinder, chimney and ...
- December 8th, 2016, 8:25 pm
- Forum: Civil Construction
- Topic: House Construction - Pre Approval Work Process
- Replies: 15
- Views: 19324
Re: House Construction - Pre Approval Work Process
FYR attached drawings in-line in subject.
My first floor and second floor is a replica. On the second floor, I have two single bedroom houses with a minor change in the space allocation and entrance facing.
My first floor and second floor is a replica. On the second floor, I have two single bedroom houses with a minor change in the space allocation and entrance facing.
- December 8th, 2016, 8:20 pm
- Forum: Civil Construction
- Topic: House Construction - Pre Approval Work Process
- Replies: 15
- Views: 19324
- December 8th, 2016, 8:16 pm
- Forum: Civil Construction
- Topic: House Construction - Pre Approval Work Process
- Replies: 15
- Views: 19324
- October 17th, 2016, 7:01 pm
- Forum: Civil Construction
- Topic: Wholesale buying places - Suggesstions
- Replies: 1
- Views: 3121
Wholesale buying places - Suggesstions
Appreciate if you can suggest for good places to buy below materials:
1. Jaguar / Hindware bathroom fittings - apart from city market
2. Current materials (branded wires and ready made switch boards) - apart from avenue road surroundings
3. Plywood boards (branded plywood sheets) -
4. Bathroom and ...
1. Jaguar / Hindware bathroom fittings - apart from city market
2. Current materials (branded wires and ready made switch boards) - apart from avenue road surroundings
3. Plywood boards (branded plywood sheets) -
4. Bathroom and ...
- October 17th, 2016, 6:25 pm
- Forum: Civil Construction
- Topic: House Construction - Pre Approval Work Process
- Replies: 15
- Views: 19324
Re: House Construction - Pre Approval Work Process
Thanks ! Second floor is completed. I'm in process of putting a small third floor room.
Yes, architects do design plans according and in sync with BBMP building plan but BBMP plan sanction norms have various clause like no of kitchens, no of floors, no of covered car parking area mandate and so on ...
Yes, architects do design plans according and in sync with BBMP building plan but BBMP plan sanction norms have various clause like no of kitchens, no of floors, no of covered car parking area mandate and so on ...