Re: Steps I did, to get my building plan approval
Posted: January 3rd, 2014, 9:54 am
Hi All,
This is an interesting site and i thought i should put my experience about getting housing plan approval..although most of the steps are already posted...however i thought i should share my experience.
Property located at: Kodipalaya Kengeri ( Near Sridhargudda)
Property dimension: 30X40 site with 650sqft built up ground floor (2 bhk) approximately 5 years old
My Requirements: G+1+2
Problem: Existing house very low compared to road & Architect suggested go for complete new building instead of doing alteration
Steps I did to get approval:
1. Got my EC with in a week's time without paying any bribe
2. Got my Khata latest extract with in 1 week with out paying any bribe
3. Got a picture presentation of my would be new house from Architect
4. Took all docs a) sale deed, b)mother sale deed c) EC d) khata extract e) Tax paid receipt f) Existing current bill g) existing housing plan approval, and went to kengeri bbm office and met a guy (bbmp staff) and struck a deal with him (for 45K) for getting approval for duplex house as i already have ground floor plan approval including everything
5. Went in the evening with all docs and all of suddenly he started telling that now it will be 55K instead of 45k, got pissed off and did not submit docs to him
6. After some research found out that my approval needs to be taken via Online and had to go to RR nagar BBMP office
7. Went there with some of my friends colleagues reference and met another case worker (very good guy) and told the charges as below
Plan print out 3k
Bribe 8k
Initial DD for Rs 125
2 DD's for the amount of 7k & 14K
Additional Rs 1000 to the guy who hands over approval plans
Note: No road cutting charges included as i already had Ground floor plan approval
8. Had to visit BBMP office 2 to 3 times as had to sign few docs and give DD's (note as read in this post, carefully examined all docs before signing for any corrections)
9. Got approval in 15 days time and was happy that i could save some money (compared to 1st guys claim)
10. Now i am in process of getting bank loan approval, its in final stages and should be done max by next week
Will keep you all posted in other forums on house construction and its process.
Note: This is a very very good forum to share your ideas, experience & best practice.
ADMIN thanks to you for getting all of us together to share our ideas & experience.
This is an interesting site and i thought i should put my experience about getting housing plan approval..although most of the steps are already posted...however i thought i should share my experience.
Property located at: Kodipalaya Kengeri ( Near Sridhargudda)
Property dimension: 30X40 site with 650sqft built up ground floor (2 bhk) approximately 5 years old
My Requirements: G+1+2
Problem: Existing house very low compared to road & Architect suggested go for complete new building instead of doing alteration
Steps I did to get approval:
1. Got my EC with in a week's time without paying any bribe
2. Got my Khata latest extract with in 1 week with out paying any bribe
3. Got a picture presentation of my would be new house from Architect
4. Took all docs a) sale deed, b)mother sale deed c) EC d) khata extract e) Tax paid receipt f) Existing current bill g) existing housing plan approval, and went to kengeri bbm office and met a guy (bbmp staff) and struck a deal with him (for 45K) for getting approval for duplex house as i already have ground floor plan approval including everything
5. Went in the evening with all docs and all of suddenly he started telling that now it will be 55K instead of 45k, got pissed off and did not submit docs to him
6. After some research found out that my approval needs to be taken via Online and had to go to RR nagar BBMP office
7. Went there with some of my friends colleagues reference and met another case worker (very good guy) and told the charges as below
Plan print out 3k
Bribe 8k
Initial DD for Rs 125
2 DD's for the amount of 7k & 14K
Additional Rs 1000 to the guy who hands over approval plans
Note: No road cutting charges included as i already had Ground floor plan approval
8. Had to visit BBMP office 2 to 3 times as had to sign few docs and give DD's (note as read in this post, carefully examined all docs before signing for any corrections)
9. Got approval in 15 days time and was happy that i could save some money (compared to 1st guys claim)
10. Now i am in process of getting bank loan approval, its in final stages and should be done max by next week
Will keep you all posted in other forums on house construction and its process.
Note: This is a very very good forum to share your ideas, experience & best practice.
ADMIN thanks to you for getting all of us together to share our ideas & experience.