Wastage added to the steel quanity ?
Posted: July 10th, 2012, 6:48 am
by sholla
I have a Item Rate contract (piece work contract) with my contractor.
While settling a recent bill I noticed that he had added 10% to the steel
used for beam/slab/staircase. There is no mention of such wastage
factor in the agreement. So, is this a normal practice ?
regards
sholla
Re: Wastage added to the steel quanity ?
Posted: July 10th, 2012, 8:19 am
by ardesarchitects
Hi,
No wastage added to the steel quantity ,if he adds it then let him show the wastage at site.you can sell the wastage at the 3/4 the price you purchased.In general they use all the waste cut pieces in chajjas, lintels etc..
Regards
Ar.Praveen.N
Ardes Architects and Interior Desinger
ardesarchitects@gmail.com
www.ardesarchitects.com
Re: Wastage added to the steel quanity ?
Posted: July 10th, 2012, 7:51 pm
by sholla
Thanks , this is very helpful.
sholla
Re: Wastage added to the steel quanity ?
Posted: July 12th, 2012, 12:58 am
by shridhark
sholla wrote:I have a Item Rate contract (piece work contract) with my contractor.
While settling a recent bill I noticed that he had added 10% to the steel
used for beam/slab/staircase. There is no mention of such wastage
factor in the agreement. So, is this a normal practice ?
regards
sholla
Item rate quotation will have wastages included in the rate itself. They are not paid for as any extra. Be firm with your contractor he is just trying to make extra money from you.